Planning ministry ‘can’t manage CPEC’


Special committee report to Senate says ministry lacks vision
in second phase of cpec there is high focus on social development and projects that are closer to the masses such as health and education photo file

In second phase of CPEC, there is high focus on social development and projects that are closer to the masses such as health and education. PHOTO: FILE

ISLAMABAD:

The Senate Special Committee on the China-Pakistan Economic Corridor (CPEC) has apprised the upper house of parliament that the planning, development and special initiatives ministry does not have the capacity to coordinate and manage projects like CPEC.

The committee states in a report that the ministry clearly lacks vision and critical thinking as an institution, adding that several lapses in the project due to mismanagement and lack of strategic planning were pointed out in the last two-and-a-half years.

“The ministry did not have the capacity to coordinate and manage a huge project like CPEC,” Committee Convener Senator Sherry Rehman stated in the report submitted before the house in the session held before the elections of chairman and deputy chairman Senate.

CPEC, an over $50 billion project, is a framework of regional connectivity, and aimed at enhancing geographical linkages by improving road, rail and air transportation system in Pakistan and in the region.

“From the outset, the committee observed that the ministry was facing issues which needed immediate response and that it clearly lacked a vision and critical thinking as an institution,” the convener stated in her message attached to the report.

Rehman has informed the house that the committee also viewed that “departments were shifting responsibility to one another and that they lacked institutional collaboration”.

After reviewing the performance and progress of the planning ministry and its various allied departments, the committee has reached the conclusion that they were “unable to formulate a clear strategy and harmonise their efforts with all stakeholders to communicate clearly to the public”.

Since CPEC is a major component of the Belt and Road Initiative (BRI) and it envisions unlocking the economic potential of Pakistan, the committee has suggested that provinces should be taken into confidence on building strong partnerships.


While giving “critical observations of the committee”, it is stated that numerous times, the committee expressed its serious concerns and reservations at the government for ignoring the demands of committee members to hold meetings and take notice of the lethargic attitude of planning ministry.

“The federal minister for planning, development and reforms was used to putting of the meetings by claiming to have been busy with projects of CPEC and his continuous visits abroad,” the report read.

In its meeting on April 17, 2019, the report stated, the committee took serious notice of the absence of the then planning minister Makhdoom Khusro Bakhtiar and directed the Senate Secretariat to issue a written notice to the federal minister.

The committee strongly criticised the minister for having left previous meetings without hearing the views of the members of the committee. The report also states that providing incomplete brief and working papers in the meetings was a routine.

The committee further observed that Special Economic Zone in Bostan, Balochistan, has received no PSDP funding and hence no progress could be achieved. “Planning Division’s unprofessional approach towards CPEC and its various umbrella projects with special reference to development of special economic zone in Balochistan and other parts of the country is disappointing.”

The report reveals that the briefings given by the planning ministry and its allied departments were “insufficient and lacked details on many aspects”. In addition, it added, that the “federal government is misrepresenting the facts on projects on Balochistan, including the SEZs, as well as the power project for Gwadar, which has been dragged in the Nepra tariff issue since 2017 and work has still not been started.”

The members of the committee stated that “no tangible progress has been achieved during last few years and despite recommendations, provision of gas and electricity supply in Boston area of Balochistan and its development as Special Economic Zone (SEZ) seems a farce.”

On several occasion, the report said, the committee showed its serious concern regarding the delay in CPEC projects and stressed the need for maintaining timelines if tangible progress is to be made. Among other things, the committee has pointed out that overlapping of responsibilities was the main reason for slow progress of projects


https://tribune.com.pk/story/2290408/planning-ministry-cant-manage-cpec

Comments

Popular posts from this blog

SSG Commando Muddassir Iqbal of Pakistan Army

“ Commando Muddassir Iqbal was part of the team who conducted Army Public School operation on 16 December 2014. In this video he reveals that he along with other commandos was ordered to kill the innocent children inside school, when asked why should they kill children after killing all the terrorist he was told that it would be a chance to defame Taliban and get nation on the side. He and all other commandos killed children and later Taliban was blamed. Muddassir Iqbal has deserted the military and now he is  with mujahedeen somewhere in AF PAK border area” For authenticity of  this tape journalists can easy reach to his home town to interview his family members or   ISPR as he reveals his army service number” Asalam o Alaikum: My name is Muddassir Iqbal. My father’s name is Naimat Ali. I belong to Sialkot divison (Punjab province), my village is Shamsher Poor and district, tehsil and post office  Narowal. Unfortunately I was working in Pakistan army. I feel embarrassed to tell yo

CPEC Jobs in Pakistan, salary details

JOBS...نوکریاں چائنہ کمپنی میں Please help the deserving persons... Salary: Salary package in China–Pakistan Economic Corridor (CPEC) in these 300,000 jobs shall be on daily wages. The details of the daily wages are as follows; Welder: Rs. 1,700 daily Heavy Duty Driver: Rs. 1,700 daily Mason: Rs. 1,500 daily Helper: Rs. 850 daily Electrician: Rs. 1,700 daily Surveyor: Rs. 2,500 daily Security Guard: Rs. 1,600 daily Bulldozer operator: Rs. 2,200 daily Concrete mixer machine operator: Rs. 2,000 daily Roller operator: Rs. 2,000 daily Steel fixer: Rs. 2,200 daily Iron Shuttering fixer: Rs. 1,800 daily Account clerk: Rs. 2,200 daily Carpenter: Rs. 1,700 daily Light duty driver: Rs. 1,700 daily Labour: Rs. 900 daily Para Engine mechanic: Rs. 1,700 daily Pipe fitter: Rs. 1,700 daily Storekeeper: Rs. 1,700 daily Office boy: Rs. 1,200 daily Excavator operator: Rs. 2,200 daily Shovel operator: Rs. 2,200 daily Computer operator: Rs. 2,200 daily Security Supervisor: Rs.

A ‘European Silk Road’

publication_icon Philipp Heimberger ,  Mario Holzner and Artem Kochnev wiiw Research Report No. 430, August 2018  43 pages including 10 Tables and 17 Figures FREE DOWNLOAD The German version can be found  here . In this study we argue for a ‘Big Push’ in infrastructure investments in greater Europe. We propose the building of a European Silk Road, which connects the industrial centres in the west with the populous, but less developed regions in the east of the continent and thereby is meant to generate more growth and employment in the short term as well as in the medium and long term. After its completion, the European Silk Road would extend overland around 11,000 kilometres on a northern route from Lisbon to Uralsk on the Russian-Kazakh border and on a southern route from Milan to Volgograd and Baku. Central parts are the route from Lyon to Moscow in the north and from Milan to Constanţa in the south. The southern route would link Central Europe with the Black Sea area and