Rs442bn accord for construction of Diamer-Bhasha dam signed


Updated May 14, 2020
Wapda chairman says Diamer-Bhasha project will be completed in 2028. — AFP/File
Wapda chairman says Diamer-Bhasha project will be completed in 2028. — AFP/File

ISLAMABAD: The government on Wednesday signed a Rs442 billion contract with a joint venture of China Power and Frontier Works Organisation (FWO) for the construction of the Diamer-Bhasha dam.

The Chinese state-run firm holds 70 per cent and the FWO, a commercial arm of the Armed Forces of Pakistan, 30pc share in the consortium. The contract covers construction of a diversion system, main dam, access bridge and the 21MW Tangir hydropower project.

The eight million acre feet (MAF) reservoir with 272-metre height will be the tallest roller compact concrete (RCC) dam in the world. It will have a spillway, 14 gates and five outlets for flushing out silt. The diversion system involves two tunnels and a diversion canal — all three having one kilometre length each. The bridge — a box girder structure — under the contract will be constructed downstream of the dam structure while the 21MW power plant will be built to meet energy requirements of the project during construction.

Prime Minister Imran Khan was briefed on the progress of the project a couple of days ago. The construction work on dam will begin in a couple of weeks.

Wapda chairman says Diamer-Bhasha project will be completed in 2028

Diamer-Bhasha dam project chief executive officer Amir Bashir Chaudhry and authorised representative of China Power Yang Jiandu signed the agreement on behalf of the Water and Power Development Authority (Wapda) and the joint venture, respectively. Water Resources Minister Faisal Vawda, Chinese Ambassador Yao Jing, Water Resources Secretary Mohammad Ashraf, Wapda chairman retired Lt Gen Muzammil Hussain, Pakistan Army engineer-in-chief Lt Gen Moazzam Ejaz and FWO director general Maj Gen Kamal Azfar attended the signing ceremony.

The Wapda chairman expressed the hope that the Diamer-Bhasha dam would be completed as per the timelines to cope with the increasing water and electricity requirements of the country. The dam project with a total financial outlay of about Rs1,406.5bn would be completed in 2028, he said.

The total financial outlay includes land acquisition and resettlement, confidence building measures for social uplift of the local people, construction of dam and power houses.

Gen Hussain said the project would have a gross storage capacity of 8.1 MAF and power generation capacity of 4,500MW, with an annual generation of 18.1bn units. However, the electromechanical and power generation project would be taken up separately at a later stage.

Wapda has already awarded a Rs27.182bn contract for dam’s consultancy services to Diamer-Bhasha Consultants Group (DBCG). The consultancy agreement includes construction design, construction supervision and contract administration of the dam project.

The DBCG joint venture comprises 12 top-ranked national and foreign consulting firms — Nespak (Pakistan), Associate Consulting Engineers (Pakistan), Mott MacDonald Pakistan, Poyry (Switzerland), Montgomery Watson and Harza (MWH) International-Stantec (USA), Dolsar Engineering (Turkey), Mott McDonald International (England), China Water Resources Beifang Investigation, Design and Research Company (China), Mirza Associates Engineering Services (Pakistan), Al-Kasib Group of Engineering Services (Pakistan), Development Management Consultant (Pakistan) and MWH Pakistan, with Nespak as the lead firm. These firms have a vast experience of providing consultancy services for mega water projects the world over.

The Council of Common Interests (CCI) had approved the project for construction in 2010, but it suffered delays because of international lending agencies which remained associated with the project but later backtracked because of opposition from India. The government has already spent about Rs170bn on the project since then on land acquisition and other expenses. In view of the lenders’ resistance, it was decided about four years ago to divide the multi-purpose project into two major components — Rs650bn worth of dam project to be constructed with the public sector funds and Rs750bn worth of power project most probably to be developed in independent power producer (IPP) mode at a later stage.

The core project development (dam structure) alone is estimated to cost almost Rs270bn. The project offers a very attractive internal economic return of 15.7pc even at a 12pc discount rate, according to project documents.

The project is designed to serve as the main storage dam of the country, besides Mangla and Tarbela dams, and its storage would be helpful for alleviating flood losses. The dam will have a 6.4 MAF usable water storage capacity.

The project is estimated to help alleviate acute irrigation shortage in the Indus basin irrigation system caused by progressive siltation of the existing reservoirs, besides substantially contributing to reduce intensity, quantum and duration of floods and reduce magnitude and frequency of floods in the River Indus downstream.

The project will also have trickledown effects on all sectors of the economy by accelerating development and creating job opportunities, besides improving availability of water and clean energy. The completion of the dam would increase the country’s storage capacity from 30 to 48 days and make power generation facilities an attractive future investment by the private sector to add 4,500MW of additional electricity to the national grid.

Published in Dawn, May 14th, 2020

Comments

Popular posts from this blog

SSG Commando Muddassir Iqbal of Pakistan Army

“ Commando Muddassir Iqbal was part of the team who conducted Army Public School operation on 16 December 2014. In this video he reveals that he along with other commandos was ordered to kill the innocent children inside school, when asked why should they kill children after killing all the terrorist he was told that it would be a chance to defame Taliban and get nation on the side. He and all other commandos killed children and later Taliban was blamed. Muddassir Iqbal has deserted the military and now he is  with mujahedeen somewhere in AF PAK border area” For authenticity of  this tape journalists can easy reach to his home town to interview his family members or   ISPR as he reveals his army service number” Asalam o Alaikum: My name is Muddassir Iqbal. My father’s name is Naimat Ali. I belong to Sialkot divison (Punjab province), my village is Shamsher Poor and district, tehsil and post office  Narowal. Unfortunately I was working in Pakistan army. I feel embarrassed to tell yo

CPEC Jobs in Pakistan, salary details

JOBS...نوکریاں چائنہ کمپنی میں Please help the deserving persons... Salary: Salary package in China–Pakistan Economic Corridor (CPEC) in these 300,000 jobs shall be on daily wages. The details of the daily wages are as follows; Welder: Rs. 1,700 daily Heavy Duty Driver: Rs. 1,700 daily Mason: Rs. 1,500 daily Helper: Rs. 850 daily Electrician: Rs. 1,700 daily Surveyor: Rs. 2,500 daily Security Guard: Rs. 1,600 daily Bulldozer operator: Rs. 2,200 daily Concrete mixer machine operator: Rs. 2,000 daily Roller operator: Rs. 2,000 daily Steel fixer: Rs. 2,200 daily Iron Shuttering fixer: Rs. 1,800 daily Account clerk: Rs. 2,200 daily Carpenter: Rs. 1,700 daily Light duty driver: Rs. 1,700 daily Labour: Rs. 900 daily Para Engine mechanic: Rs. 1,700 daily Pipe fitter: Rs. 1,700 daily Storekeeper: Rs. 1,700 daily Office boy: Rs. 1,200 daily Excavator operator: Rs. 2,200 daily Shovel operator: Rs. 2,200 daily Computer operator: Rs. 2,200 daily Security Supervisor: Rs.

A ‘European Silk Road’

publication_icon Philipp Heimberger ,  Mario Holzner and Artem Kochnev wiiw Research Report No. 430, August 2018  43 pages including 10 Tables and 17 Figures FREE DOWNLOAD The German version can be found  here . In this study we argue for a ‘Big Push’ in infrastructure investments in greater Europe. We propose the building of a European Silk Road, which connects the industrial centres in the west with the populous, but less developed regions in the east of the continent and thereby is meant to generate more growth and employment in the short term as well as in the medium and long term. After its completion, the European Silk Road would extend overland around 11,000 kilometres on a northern route from Lisbon to Uralsk on the Russian-Kazakh border and on a southern route from Milan to Volgograd and Baku. Central parts are the route from Lyon to Moscow in the north and from Milan to Constanţa in the south. The southern route would link Central Europe with the Black Sea area and