CPEC Western Corridor’s completion next year to boost economy of remote areas

Thenews.com.pk


ISLAMABAD: The 292-km long mega Western Corridor project will help usher an era of economic prosperity in some of the country’s most underdeveloped regions, officials said Sunday.China-Pak...

ShareNext Story >>>

ISLAMABAD: The 292-km long mega Western Corridor project will help usher an era of economic prosperity in some of the country’s most underdeveloped regions, officials said Sunday.

China-Pak Economic Corridor (CPEC) Chairman and Special Assistant to the Prime Minister on Information Lt-Gen (R) Asim Saleem Bajwa last week tweeted completion of 69 percent of work on a key leg of the Rs 212 billion worth Corridor project.

A four-lane expressway from Hakla near Islamabad to Dera Ismail Khan will reduce travel time between Dera Ismail Khan and Islamabad from five hours to two and half hours.

The first component following a virgin alignment was planned from Hakla near Islamabad from M-2 motorway to Yarik at border of KP and Balochistan. The second part of the corridor is 540 km Yarik-Zhob-Quetta National Highway to be upgraded to motorway standard, thus reducing distance from Islamabad to Quetta to only 830 kms and eight hours travel time on this new motorway standard four-lane expressway.

The estimated cost of upgrading Yarik to Quetta via Zhob section is Rs142b. The Hakla-Yarik section which has been reported to be 69% complete by the CPEC chairman will pass through Pindigheb, Tarap in Attock, Duadkhel and Isakhel in Mianwali, and Kundal, Abulkhail and Yarik in Dera Ismail Khan district.

The Hakla-Yarik section will have 12 interchanges at Dhok Sayedan, Thati Kalran (Fateh Jang), Kharpa (Pindigheb), Tarap (Jandh), Daud Khel, Kot Balian, Isakhel (Mianwali), Kundal, Abul Khail and Yarik in Dera Ismail Khan. The project has four service areas at distance of 60 kms, and three large bridges over Indus, Swan, and Khuram rivers.

National Highway Authority (NIH) monitoring documents available with The News show that the project for sake of speedy implementation was divided into five packages with each having a stretch of some 60 kms. Contracts were allocated to different parties.

Package One is from Yarik to Rehmani Khel measuring 55 kms and costing Rs13b. The contract has been awarded to National Logistics Cell (NLC), which has completed 85% of the work, as reported in NHA documents. The package was started in September 2016, and planned completion date was August 2018. It is expected to be completed by end of the year.

Package Two is from Rehmani Khel to Kot Balian spanning over 72 kms, and will cost Rs 28b. So far 75pc work on this key package has been completed. Work on this package started in July 2017, and is expected to be completed by April 2021.

This package is further sub-divided into four sub-packages and has been constructed by different contracting firms - SKB, Khalid Rauf & Co and SMADB-Sardar and Sharaf Balouch Company.

Package Three is from Kot Balian in Mianwali to Tarap in Attock. It is 52-km long, will cost Rs21b and 75% work on this section has been done so far. This component has two large bridges on the River Indus and Swan. The completion date is end-2020. The Frontier Works Organization is the contractor.

Package Four runs from Tarap to Pindigheb, is 51 km long and will cost Rs21.3b. Sixty-one percent work has been accomplished so far. The progress is relatively slow. It is expected to be complete by end-2020.

It is a joint venture between Limak and ZKB (Zahir Khan Brothers) contractors. Package Five is from Pindigheb to Hakla on M-2 in Islamabad. This component measures 63 kms and will cost about Rs17b. It is being constructed by the same joint venture and is the slowest with only 47% progress. It is expected to finish by end of 2020.

Cumulative cost of all five packages as per NHA documents is Rs110b. An amount of Rs12b has been spent on land acquisition for this state of the art motorway. In background discussions, the NHA and Planning Commission officials cite low financial allocations by the government as key reason for sluggish pace of work and delayed completion. In the Public Sector Development Programme (PSDP) for 2019-2020 only Rs11.5b were allotted and only Rs2.5b have been released so far. Till date, an amount of Rs80b has been spent on this key inter-provincial project, they said and hoped that the western corridor would be completed fast after General Asim Bajwa took over as CPEC chairman.

Incidentally, the two areas which will be major beneficiaries of this mega project are the constituencies of Prime Minister Imran Khan in Mianwalli and Jamiat Ulemae Islam-Fazl chief Maulana Fazlur Rehman in Dera Ismail Khan. The officials say the western corridor is wholly financed by the Pakistan government development allocation in the PSDP

Comments

Popular posts from this blog

SSG Commando Muddassir Iqbal of Pakistan Army

“ Commando Muddassir Iqbal was part of the team who conducted Army Public School operation on 16 December 2014. In this video he reveals that he along with other commandos was ordered to kill the innocent children inside school, when asked why should they kill children after killing all the terrorist he was told that it would be a chance to defame Taliban and get nation on the side. He and all other commandos killed children and later Taliban was blamed.
Muddassir Iqbal has deserted the military and now he is  with mujahedeen somewhere in AF PAK border area”
For authenticity of  this tape journalists can easy reach to his home town to interview his family members or   ISPR as he reveals his army service number”
Asalam o Alaikum: My name is Muddassir Iqbal. My father’s name is Naimat Ali. I belong to Sialkot divison (Punjab province), my village is Shamsher Poor and district, tehsil and post office  Narowal. Unfortunately I was working in Pakistan army. I feel embarrassed to tell you …

CPEC Jobs in Pakistan, salary details

JOBS...نوکریاں چائنہ کمپنی میںPlease help the deserving persons...Salary:Salary package in China–Pakistan Economic Corridor (CPEC) in these 300,000 jobs shall be on daily wages. The details of the daily wages are as follows;Welder: Rs. 1,700 dailyHeavy Duty Driver: Rs. 1,700 dailyMason: Rs. 1,500 dailyHelper: Rs. 850 dailyElectrician: Rs. 1,700 dailySurveyor: Rs. 2,500 dailySecurity Guard: Rs. 1,600 dailyBulldozer operator: Rs. 2,200 dailyConcrete mixer machine operator: Rs. 2,000 dailyRoller operator: Rs. 2,000 dailySteel fixer: Rs. 2,200 dailyIron Shuttering fixer: Rs. 1,800 dailyAccount clerk: Rs. 2,200 dailyCarpenter: Rs. 1,700 dailyLight duty driver: Rs. 1,700 dailyLabour: Rs. 900 dailyPara Engine mechanic: Rs. 1,700 dailyPipe fitter: Rs. 1,700 dailyStorekeeper: Rs. 1,700 dailyOffice boy: Rs. 1,200 dailyExcavator operator: Rs. 2,200 dailyShovel operator: Rs. 2,200 dailyComputer operator: Rs. 2,200 dailySecurity Supervisor: Rs. 2,200 dailyCook for Chinese food: Rs. 2,000 dailyCook…

Historical relationship between Kurd and Baloch.

The Kurds are the ethnical group living in a region known as Kurdistan which is divided into Iraq, Syria, Turkey and Iran. They  are struggling for an independent region since decades and they are famous for their female guerrilla fighters.        On 25 September 2017, the referendum for an independent Kurdish region  was held in Iraq with a turn out of 72 %.   On this important occasion, the historical relation between Kurd and Baloch people is worth discussing.       When it comes to history, every nation tends to find its roots and origin. Same goes with the Baloch people. The Baloch people are always curious  about  finding their roots in history. Even if you  talk to a shepherd in Balochistan, he will be curious to talk about his  tribal or ethnical roots.      The Balochs have always conveyed the history to the next generations in different mediums like poems etc. No Baloch before 20th century had written books on  history  or origin of the Baloch nation .
        Balochs…