East Africa's joint mega railway project at the crossroads


Ongoing works at the Standard gauge Railway (SGR) Project, Phase 2A of Nairobi to Naivasha at the Inland Container Deport (ICD) on June 23, 2018. Its construction is funded by China. FILE PHOTO | NMG 

In Summary

The planned 1,500km-long railway from Mombasa to Kigali was expected to be completed by 2018, but only Kenya has completed the initial phase of the project from Mombasa to Nairobi.It is understood that China had offered to finance the entire joint railway project connecting Kenya, Uganda and Rwanda, but the idea was dropped after Kampala changed its mind.The standard gauge railway is part of the Northern Corridor infrastructure project designed to connect Mombasa to Malaba on the border with Uganda, and onward to Kampala, Uganda’s capital city and eventually Kigali in Rwanda.

ADVERTISEMENT

By JAMES ANYANZWA
More by this Author

East Africa's ambitious standard gauge railway line linking the port of Mombasa to the landlocked countries in the region has fallen behind schedule largely due to financing constraints, doubts over its economic viability, the cost of construction and indecisiveness on the part of some partner states to build their respective sections.

The planned 1,500km-long railway from Mombasa to Kigali was expected to be completed by 2018, but only Kenya has completed the initial phase of the project from Mombasa to Nairobi.

Although Rwanda is part of this grand regional rail network, it has focused more on the Isaka-Kigali railway project seeking to link the capital Kigali with Tanzania.

The 571-kilometre railway, whose construction was planned to start last in December, is expected to improve trade between the two countries.

The project, to cost $2.5 billion — of which Tanzania will pay $1.3 billion and Rwanda $1.2 billion — is estimated to be cheaper by close to $200 million compared with if Rwanda had opted for the Kenyan route, connecting through Uganda.

The Ugandan section of the standard gauge railway was launched in October 2014 and although the country has completed the feasibility and designs for the 273km-long line between Malaba in Kenya and Kampala, the construction is yet to begin, with Kampala attributing the delay to lack of financing and Kenya’s failure to complete its part of the project by extending the line to Malaba.

RELATED CONTENT

Uganda focuses on old railwayRevealed: Hidden traps in Kenya SGR deal with ChinaBuilding of Isaka-Kigali railway to start in DecemberTanzania secures $1.46b SGR loan from Stanchart

The Ugandan section is estimated to cost $2.3 billion.

Rwanda, on the other hand, has completed the preliminary engineering design of the new line from Kampala to Kigali, via Mirama Hills, and is seeking financing. It is understood that Kigali has been in talks with China’s Export-Import Bank for a $1.2 billion loan.

But even if Rwanda were to get funding, it would not proceed with the project without assurance that Ugandan will do its part.

It is understood that China had offered to finance the entire joint railway project connecting Kenya, Uganda and Rwanda, but the idea was dropped after Kampala changed its mind, and gave priority to developing a railway link to South Sudan instead.

Last year, Uganda’s Finance Minister Matia Kasaija told Daily Monitor that the government had suspended the standard gauge railway project and has instead turned attention to revamping the old metre-gauge railway network.

“It is apparent the SGR is going to take us a lot of time to complete. First, we have to wait for Kenya to reach the Malaba border point then we can start,” Mr Kasaija said.

Kenya has secured Chinese funding to extend the line from Nairobi to Naivasha in the Central Rift, at an estimated cost of Ksh150 billion ($1.5 billion) and the work on the project is on-going.

The 120km-long Nairobi-Naivasha line is the first of the three segments that make up the second phase of the railway that ends in Malaba town on the Kenya-Uganda border.

However, Kenya is yet to secure financing for the last two segments of the project from Naivasha to Kisumu and then to Malaba, amid public concern that the country’s ballooning debt and particularly the Chinese loans, have put national assets at risk of being seized by the Chinese government in the event of loan default.

In its first year of operation to June 2018, the Mombasa to Nairobi cargo and passenger services suffered a loss of Ksh10 billion ($100 million), according to Kenya’s Ministry of Transport and Infrastructure.

The magnitude of the losses has raised concerns over the economic viability of the first major railway transport infrastructure that Kenya has developed since Independence.

The initial phase of the Kenyan section of the project, 609km-long line from Mombasa to Nairobi, was completed in 2017 at a cost of Ksh327 billion ($3.27 billion), with the China Exim Bank providing 90 per cent of the financing while the remaining 10 per cent was contributed by the Kenyan government.

The phase between Naivasha and Malaba, whose funding has not been secured, is expected to cost Ksh500 billion ($5 billion).

But Kenya has argued that it would not be necessary to extend its line to Malaba if other land locked countries are not committed to the project.

The standard gauge railway is part of the Northern Corridor infrastructure project designed to connect Mombasa to Malaba on the border with Uganda, and onward to Kampala, Uganda’s capital city and eventually Kigali in Rwanda, with a branch line to Kisumu, and a northern line to Juba in South Sudan through Kasese and Pakwach.


https://www.theeastafrican.co.ke/business/East-Africa-joint-mega-railway-project-at-the-crossroads/2560-4954932-6la96xz/index.html

Comments

Popular posts from this blog

SSG Commando Muddassir Iqbal of Pakistan Army

“ Commando Muddassir Iqbal was part of the team who conducted Army Public School operation on 16 December 2014. In this video he reveals that he along with other commandos was ordered to kill the innocent children inside school, when asked why should they kill children after killing all the terrorist he was told that it would be a chance to defame Taliban and get nation on the side. He and all other commandos killed children and later Taliban was blamed.
Muddassir Iqbal has deserted the military and now he is  with mujahedeen somewhere in AF PAK border area”
For authenticity of  this tape journalists can easy reach to his home town to interview his family members or   ISPR as he reveals his army service number”
Asalam o Alaikum: My name is Muddassir Iqbal. My father’s name is Naimat Ali. I belong to Sialkot divison (Punjab province), my village is Shamsher Poor and district, tehsil and post office  Narowal. Unfortunately I was working in Pakistan army. I feel embarrassed to tell you …

CPEC Jobs in Pakistan, salary details

JOBS...نوکریاں چائنہ کمپنی میںPlease help the deserving persons...Salary:Salary package in China–Pakistan Economic Corridor (CPEC) in these 300,000 jobs shall be on daily wages. The details of the daily wages are as follows;Welder: Rs. 1,700 dailyHeavy Duty Driver: Rs. 1,700 dailyMason: Rs. 1,500 dailyHelper: Rs. 850 dailyElectrician: Rs. 1,700 dailySurveyor: Rs. 2,500 dailySecurity Guard: Rs. 1,600 dailyBulldozer operator: Rs. 2,200 dailyConcrete mixer machine operator: Rs. 2,000 dailyRoller operator: Rs. 2,000 dailySteel fixer: Rs. 2,200 dailyIron Shuttering fixer: Rs. 1,800 dailyAccount clerk: Rs. 2,200 dailyCarpenter: Rs. 1,700 dailyLight duty driver: Rs. 1,700 dailyLabour: Rs. 900 dailyPara Engine mechanic: Rs. 1,700 dailyPipe fitter: Rs. 1,700 dailyStorekeeper: Rs. 1,700 dailyOffice boy: Rs. 1,200 dailyExcavator operator: Rs. 2,200 dailyShovel operator: Rs. 2,200 dailyComputer operator: Rs. 2,200 dailySecurity Supervisor: Rs. 2,200 dailyCook for Chinese food: Rs. 2,000 dailyCook…

Historical relationship between Kurd and Baloch.

The Kurds are the ethnical group living in a region known as Kurdistan which is divided into Iraq, Syria, Turkey and Iran. They  are struggling for an independent region since decades and they are famous for their female guerrilla fighters.        On 25 September 2017, the referendum for an independent Kurdish region  was held in Iraq with a turn out of 72 %.   On this important occasion, the historical relation between Kurd and Baloch people is worth discussing.       When it comes to history, every nation tends to find its roots and origin. Same goes with the Baloch people. The Baloch people are always curious  about  finding their roots in history. Even if you  talk to a shepherd in Balochistan, he will be curious to talk about his  tribal or ethnical roots.      The Balochs have always conveyed the history to the next generations in different mediums like poems etc. No Baloch before 20th century had written books on  history  or origin of the Baloch nation .
        Balochs…