Poor construction standard found in CPEC road project


The Newspaper's Staff Reporter

ISLAMABAD: Poor standard of construction has been found in a road project of the China-Pakistan Econo­mic Corridor (CPEC) in Balochistan.

The Zhob-Mughalkot Road (N-50) has two packages and Package-I is being built by M/s Zahid Khan & Brothers (ZKB).

Maqbool Associates, which had submitted the lowest bid, won the contract, but the National Highway Authority (NHA) reportedly awarded it to ZKB, though the latter had offered higher rates, without asking it to match the lowest bid.

Former prime minister Nawaz Sharif had inaugurated the project in January 2016.

ARTICLE CONTINUES AFTER AD

It has been learnt that an 11km portion of the 41km Zhob-Killi Khudae Nazar road (Package-I) was badly damaged, while ditches and cracks had also appeared on its other portions.

According to an NHA document, the 41km Zhob-Killi Khudae Nazar road was to be reconstructed by Limak-ZKB Joint Venture at a cost Rs4.8 billion under Package-I, and the 40km Killi Khudae Nazar-Mughalkot road by Maqbool-Zarghoon Joint Venture at cost of Rs4bn under Package-II.

At the same time, two separate projects had been awarded for N-70. A firm, Umar Jan, will construct the road from Qilla Saifullah to Loralai at a cost Rs4.50bn under Package-I, while Maqbool-Zarghoon JV will construct the road from Loralai to Waigum Rud at a cost of Rs3.02bn under Package-II.

According to the NHA document, Maqbool-Zarghoon JV had submitted the lowest bids for all four projects, but it was not considered for Package-I of N-50 and Package-I of N-70 and the contracts had been awarded to the second lowest bidders (ZKB and Umar Jan). Even the second lowest bidders had not been asked to match the lowest bids.

Maqbool-Zarghoon JV has expressed concern over non-consideration of its bids and wrote many letters to the NHA, claiming that the contracts had been awarded ‘illegally’ to the second lowest bidders.

When contacted, an NHA spokesman said the project was under construction and had not yet been completed.

He said: “Such problems/damages do often happen during construction and its rectification remains the responsibility of the contractor/consultant. It is always ensured that all such issues are fully addressed before the project is completed and opened to traffic.”

He said the 81km long Zhob-Mughalkot project was divided into two lots and awarded to ZKB and Maqbool-Zarghoon JV, respectively. Maqbool-Zarghoon JV challenged the award of lot-1 in court where they lost the case and the Islamabad High Court upheld the NHA’s decision.

Although the issue caused a delay in execution of the project, the NHA has managed to overcome unnecessary loss of time and the project was set to complete during the current year.

Published in Dawn, May 7th, 2018

https://www.dawn.com/news/1406141

Comments

Popular posts from this blog

Balochistan to establish first medical university

https://www.dawn.com/news/1366135

The Newspaper's Staff CorrespondentOctober 25, 2017QUETTA: The provincial cabinet on Tuesday approved the draft for establishing a medical university in Balochistan.Health minister Mir Rehmat Saleh Baloch made the announcement while speaking at a press conference after a cabinet meeting.“The cabinet has approved the draft of the medical university which would be presented in the current session of the Balochistan Assembly,” he said, adding with the assembly’s approval the Bolan Medical College would be converted into a medical university.Published in Dawn, October 25th, 2017

CPEC Jobs in Pakistan, salary details

JOBS...نوکریاں چائنہ کمپنی میںPlease help the deserving persons...Salary:Salary package in China–Pakistan Economic Corridor (CPEC) in these 300,000 jobs shall be on daily wages. The details of the daily wages are as follows;Welder: Rs. 1,700 dailyHeavy Duty Driver: Rs. 1,700 dailyMason: Rs. 1,500 dailyHelper: Rs. 850 dailyElectrician: Rs. 1,700 dailySurveyor: Rs. 2,500 dailySecurity Guard: Rs. 1,600 dailyBulldozer operator: Rs. 2,200 dailyConcrete mixer machine operator: Rs. 2,000 dailyRoller operator: Rs. 2,000 dailySteel fixer: Rs. 2,200 dailyIron Shuttering fixer: Rs. 1,800 dailyAccount clerk: Rs. 2,200 dailyCarpenter: Rs. 1,700 dailyLight duty driver: Rs. 1,700 dailyLabour: Rs. 900 dailyPara Engine mechanic: Rs. 1,700 dailyPipe fitter: Rs. 1,700 dailyStorekeeper: Rs. 1,700 dailyOffice boy: Rs. 1,200 dailyExcavator operator: Rs. 2,200 dailyShovel operator: Rs. 2,200 dailyComputer operator: Rs. 2,200 dailySecurity Supervisor: Rs. 2,200 dailyCook for Chinese food: Rs. 2,000 dailyCook…

China’s 'Digital Silk Road': Pitfalls Among High Hopes

https://thediplomat.com/2017/11/chinas-digital-silk-road-pitfalls-among-high-hopes/


Will information and communication technologies help China realize its Digital Silk Road?By Wenyuan WuNovember 03, 2017In his speech at the opening ceremony of China’s 19th Party Congress, President Xi Jinping depicted China as a model of scientific and harmonious development for developing nations. Xi’s China wants to engage the world through commerce but also through environmental protection and technological advancement. This includes Beijing’s efforts to fight climate change with information and communication technologies (ICTs) that it plans to export along its “One Belt One Road” initiative (OBOR). Xi may have ambitious plans, but could China be throwing up obstacles in its own way?In his speech, the Chinese president emphasized the need to modernize the country’s environmental protections. The Chinese state is taking an “ecological civilization” approach to development and diplomacy, with a natio…