Another major CPEC project delayed

APRIL 27, 2018

ISLAMABAD: The Economic Coordination Committee (ECC) of the federal cabinet decided to extend the financial close of the 660 kilovolt high-voltage direct current (HVDC) Matiari-Lahore transmission line by seven months till the 1st of December, 2018.

The extension means that the project—initially slated to become operational in September 2017—now faces a three year delay, ostensibly to align it with the coal-fired projects under development in Thar and near Karachi.

The project is also plagued by squabbling over wheeling charges and tax concessions, and the initial cost of the project has now risen from US$1.5 billion to US$1.7 billion.

The Chinese companies China Electric Power Equipment and Technology Company Limited (CET) of State Grid Corporation of China (SGCC) are executing the project.

Moreover, the ECC also borrowed Rs 100 billion from commercial banks to ease the circular debt that had started creeping up a mere month before Ramazan.

This is the second time in the past one month that the government has been forced to resort to commercial borrowing to improve the circular debt, which is estimated to have crossed Rs 1 trillion


https://dailytimes.com.pk/233115/another-major-cpec-project-delayed/

Comments

Popular posts from this blog

The Rise of China-Europe Railways

https://www.csis.org/analysis/rise-china-europe-railways

The Rise of China-Europe RailwaysMarch 6, 2018The Dawn of a New Commercial Era?For over two millennia, technology and politics have shaped trade across the Eurasian supercontinent. The compass and domesticated camels helped the “silk routes” emerge between 200 and 400 CE, and peaceful interactions between the Han and Hellenic empires allowed overland trade to flourish. A major shift occurred in the late fifteenth century, when the invention of large ocean-going vessels and new navigation methods made maritime trade more competitive. Mercantilism and competition among Europe’s colonial powers helped pull commerce to the coastlines. Since then, commerce between Asia and Europe has traveled primarily by sea.1Against this historical backdrop, new railway services between China and Europe have emerged rapidly. Just 10 years ago, regular direct freight services from China to Europe did not exist.2 Today, they connect roughly 35 Chinese…

CPEC Jobs in Pakistan, salary details

JOBS...نوکریاں چائنہ کمپنی میںPlease help the deserving persons...Salary:Salary package in China–Pakistan Economic Corridor (CPEC) in these 300,000 jobs shall be on daily wages. The details of the daily wages are as follows;Welder: Rs. 1,700 dailyHeavy Duty Driver: Rs. 1,700 dailyMason: Rs. 1,500 dailyHelper: Rs. 850 dailyElectrician: Rs. 1,700 dailySurveyor: Rs. 2,500 dailySecurity Guard: Rs. 1,600 dailyBulldozer operator: Rs. 2,200 dailyConcrete mixer machine operator: Rs. 2,000 dailyRoller operator: Rs. 2,000 dailySteel fixer: Rs. 2,200 dailyIron Shuttering fixer: Rs. 1,800 dailyAccount clerk: Rs. 2,200 dailyCarpenter: Rs. 1,700 dailyLight duty driver: Rs. 1,700 dailyLabour: Rs. 900 dailyPara Engine mechanic: Rs. 1,700 dailyPipe fitter: Rs. 1,700 dailyStorekeeper: Rs. 1,700 dailyOffice boy: Rs. 1,200 dailyExcavator operator: Rs. 2,200 dailyShovel operator: Rs. 2,200 dailyComputer operator: Rs. 2,200 dailySecurity Supervisor: Rs. 2,200 dailyCook for Chinese food: Rs. 2,000 dailyCook…

Balochistan to establish first medical university

https://www.dawn.com/news/1366135

The Newspaper's Staff CorrespondentOctober 25, 2017QUETTA: The provincial cabinet on Tuesday approved the draft for establishing a medical university in Balochistan.Health minister Mir Rehmat Saleh Baloch made the announcement while speaking at a press conference after a cabinet meeting.“The cabinet has approved the draft of the medical university which would be presented in the current session of the Balochistan Assembly,” he said, adding with the assembly’s approval the Bolan Medical College would be converted into a medical university.Published in Dawn, October 25th, 2017